The Lærdal Tunnel
The Lærdal Tunnel (E16) has a pilot car as of 27 Nov at 16:10.
- E16LærdalstunnelenPilot car
Closures during the upgrade
- NightClosed 18:00–06:00, except the night to Sunday
- Saturday eveningOpen, with manual traffic control
- DayOpen, pilot car or traffic lights
- Daytime waitUp to 15 minutes
- Period16 Nov 2026 – summer 2028
- CompletedAutumn 2029
- Evening bus17:30, 20:30 and 22:30 from both ends
If you arrive after 18:00, the next chance to drive through is at 06:00 the next morning. After summer 2028 the night closures get shorter. The evening bus is for people living in Aurland and Lærdal, and ambulances, fire engines and police are let through as quickly as possible. The times are the Roads Administration's plan; the status at the top follows their messages and shows it if anything changes.
When the tunnel is closed
At night you need another road between east and west Norway. The Norwegian Public Roads Administration recommends Rv. 7 over Hardangervidda, and the Lærdal Tunnel is kept open when Hardangervidda is closed by winter weather. Status now:
Hol–Aurland (Fv. 50) comes down in Aurland and avoids the tunnel. Between Sogn and Bergen you can drive Vikafjellet when it is open; the Vangsnes–Hella ferry has two extra night departures between 02:00 and 06:00. The mountain road over Aurlandsfjellet is closed in winter.
Why is the tunnel being upgraded?
The Lærdal Tunnel is more than 25 years old, and much of its technical equipment has reached the end of its life. The upgrade will bring the tunnel up to the Norwegian tunnel safety regulations, which are based on the EU rules for long tunnels. The Roads Administration has been upgrading national road tunnels across Norway since 2015 and calls this the world's longest tunnel upgrade. The work includes:
- 28 new technical buildings inside the tunnel, blasted out of the rock, each with a lay-by
- Emergency cabinets with a telephone and fire extinguishers every 250 metres
- New ventilation and fans that pull the air out through the side tunnel to Tynjadalen
- New lighting and emergency lights, CCTV, emergency radio and DAB radio the traffic centre can break into with messages
- Larger turning bays and new barriers and signs
- A treatment basin for the tunnel's wash water
Blasting inside the tunnel is why it has to close at night. Once the heaviest work is done, more traffic can be let through. Skanska and Vassbakk & Stol hold the contract, worth NOK 1.6 billion.
About the Lærdal Tunnel
- Length24.5 km (24,509 m)
- RecordWorld's longest road tunnel
- RoadE16, Aurland – Lærdal
- Opened27 November 2000
- Mountain hallsThree, about every six kilometres
- Traffic2,100 vehicles a day

The Lærdal Tunnel was built from 1995 to 2000 and completed a winter-safe road without ferries between Oslo and Bergen. It took over from the Gotthard road tunnel in Switzerland as the world's longest road tunnel. It runs from Nyheim, just east of Aurlandsvangen, to Håbakken, 5.5 km south of Lærdalsøyri.
The three mountain halls have blue light in the roof and yellow light along the ground, meant to feel like sunrise and give a break from the long drive. The tunnel has one tube with one lane in each direction and no emergency exits. About a quarter of the traffic is heavy vehicles.


Questions and answers
Is the Lærdal Tunnel open now?
The Lærdal Tunnel (E16) has a pilot car as of 27 Nov at 16:10.
When is the Lærdal Tunnel closed?
During the upgrade the tunnel is closed every night from 18:00 to 06:00, except the night to Sunday. In the daytime it is open, but expect a pilot car or traffic lights and up to 15 minutes of waiting.
Is the Lærdal Tunnel open on Saturday evening?
Yes. The tunnel is not closed on the night to Sunday, but traffic is controlled manually.
How long will the Lærdal Tunnel be closed at night?
The night closures started on 16 November 2026 and will last about a year and a half, until summer 2028. After that the night closures get shorter. The whole upgrade is expected to be finished in autumn 2029.
Why is the Lærdal Tunnel closed?
The tunnel is being upgraded to meet today's safety requirements for long tunnels: new technical buildings, emergency cabinets, ventilation, lighting and monitoring. Blasting inside the tunnel means it has to close at night.
Which road can I take when the Lærdal Tunnel is closed?
The Norwegian Public Roads Administration recommends Rv. 7 over Hardangervidda. Other routes between east and west are Hol–Aurland (Fv. 50) and Haukelifjell (E134), and between Sogn and Bergen, Vikafjellet with the Vangsnes–Hella ferry. The tunnel is kept open when Hardangervidda is closed by winter weather.
Is the Lærdal Tunnel the longest tunnel in the world?
It is the world's longest road tunnel, 24.5 km. There are longer railway tunnels, such as the Gotthard Base Tunnel in Switzerland.
Sources: Norwegian Public Roads Administration: E16 Lærdal Tunnel (Norwegian) · Wikipedia: Lærdal Tunnel
Mountain passes
- Hemsedalsfjellet
- Hardangervidda
- Hol–Aurland
- Vikafjellet
- Tyin–Årdal
- Haukelifjell
- Filefjell
- Strynefjellet
- Sognefjellet
- Utvikfjellet
- Gaularfjellet
- Hellandsbygd–Breiborg
- Breiborg–Røldal
- Matre–Bjordalen
- Sirdal–Lysebotn
- Aurlandsfjellet
- Dovrefjell
- Friisvegen
- Valdresflye
- Gamle Strynefjellsvegen
- Imingfjell
- Trollstigen
- Geiranger–Langvatn
- Venabygdsfjellet
- Tyin–Eidsbugarden
- Dagalifjellet
- Haglebu
- Hjerkinn
- Bekkarfjord–Hopseidet
- Skarsvåg–Nordkapp